Tuesday 31 March 2015

Complete information & Analysis on Talwar class frigates designed and built by Russia for the Indian Navy. Part 2








The ceremony of laying TFR "Admiral Grigorovich" section of the mortgage and the mortgage board, GCC "Amber", Kaliningrad, 18.12.2010 (photo I.A.Mihaylova and RIA "Novosti", http://forums.airbase.ru ).
- 2011 May 6 - on CVD "Amber" started harvesting hull structures for TFR "Admiral Essen" pr.11356M. Completed assembly of the 4th block TFR "Admiral Grigorovich."
- 2011 July 8 - on CVD "Amber" laid the second ship of the contract - TFR "Admiral Essen" pr.11356M of a series of three TFR for the Russian Navy.



Shifting boards and ceremony TFR "Admiral Essen" pr.11356 on CVD "Amber", Kaliningrad, 08.07.2011, the ( http://forums.airbase.ru ).Construction of housing TFR "Admiral Grigorovich" pr.11356 on CVD "Amber", Kaliningrad, 08.07.2011, the ( http://forums.airbase.ru ).



Construction Corps TFR "Admiral Grigorovich" pr.11356 on CVD "Amber", Kaliningrad, November 2011 (photo - vvv39,http://forums.airbase.ru ).
- 2011 December 20 - in the media reported that construction work on the TFR for the Russian Navy, "Admiral Grigorovich" and "Admiral Essen."
- 2012 07 February - the newspaper "Kommersant", citing sources in the Russian Defense Ministry reported that the modified program of armaments to 2020 the number of TFR pr.11356 - 6 units - that confirms the earlier figures.
- 29 February 2012 - the media reported on the plans to put in the Russian Navy until 2016 6 TFR pr.11356. On CVD "Amber" laid the third ship to the Russian Navy - "Admiral Makarov".
- 2012 September 14 - the media reported about the plans bookmarks in October 2012 the fourth frigate pr.11356 for the Russian Navy.As of now the state of construction of the first three ships:
- "Admiral Grigorovich" - the body formed in 2013, is expected to hit the water.
- "Admiral Essen" - the case is almost formed.
- "Admiral Makarov" - the case is in the stage of formation blocks.
- 2012 October 12 - RIA "Novosti" spread information about the upcoming October 12 frigate pr.11356 fourth tab for the Russian Navy - "Admiral Butakov" ( source ). During the day the ceremony did not take place - according to unconfirmed information, the ceremony moved to a later date.

Left on the slipway frigate "Admiral Grigorovich" zav.№01357, GCC "Amber", Kaliningrad, 27.10.2012 (photo - 39rus,http://forums.airbase.ru ).
- 2013 March - Baltic Plant (St. Petersburg) started manufacturing three PU ship missile system "Caliber" for pr.11356 frigates being built for the Russian Navy in the GCC "Amber". Under the contract, the delivery of all three CP should be held before the end of 2014 №№4-6 frigates will also be equipped with PU production Baltic plant. In addition, in early 2013 the St. Petersburg shipyard produced three pairs of propellers for the first three Russian frigates, and recently signed an agreement to manufacture another six screws - for the second three ships. ( source ).
- 2013 March 7 - the frigate "Admiral Makarov" Construction on the GCC "Amber" began the final stage of the formation of the body - the assembly bow. Completion of the housing assembly is expected in May 2013

Start docking bow of the hull of the frigate "Admiral Makarov" CVD "Amber", 03.07.2013 (photo - S.Mihaylov, Forward! №4 / 2013).
- 2013 June 14 - completed docked nose island housing the frigate "Admiral Makarov" and the rest of the ship. Completing the docking work is expected in July 2013

Mortgage section frigate "Admiral Butakov" pr.11356R on CVD "Amber", the beginning of July 2013 (photo - S.Mihaylov,http://www.shipyard-yantar.ru ).

Shifting boards TFR "Admiral Butakov" pr.11356, photo from 12.07.2013, the bookmark ( http://function.mil.ru ).
- 2013 July 12 - reported that the GCC "Yantar" in Kaliningrad on the newly built headquarters frigate "Admiral Grigorovich" pr.11356R completed loading of gas turbine engines and propulsion gear. Mounted propeller shafts. Soon his installation of a diesel generator and milling parts GGTA.
- 2014 04 February - the media reported that the head pr.11356 frigate for the Russian Navy, "Admiral Grigorovich" summer 2014 is planned to test SAM "Calm-1" with the launcher 3S90E.1 vertical launch 12 rockets.
- 2014 March 14 - at the Shipyard "Yantar" water lowered head pr.11356 frigate for the Russian Navy, "Admiral Grigorovich."

Launch ceremony of the head of the frigate pr.11356 for the Russian Navy, "Admiral Grigorovich," Shipyard "Yantar", Kaliningrad, 03/14/2014 (photo - Igor Zarembo, http://ria.ru/ ).

Pr.11356R head frigate for the Russian Navy, "Admiral Grigorovich," Shipyard "Yantar", Kaliningrad, 19/03/2014 (photo - Drakon 64,http://forums.airbase.ru ).

Pr.11356R head frigate for the Russian Navy, "Admiral Grigorovich," Shipyard "Yantar", Kaliningrad, April 2014 (photo - oleg12226,http://forums.airbase.ru ).
- 2014 May 15 - on the TFR "Admiral Grigorovich" installed artillery unit A-190-01 ( source ) .. - 18 June 2014 - on the TFR "Admiral Grigorovich" shipped the first of two torpedo tubes DTA-53-11356 . Factory Press ( source ) noted that the progress of construction of the ship significantly hinders short supply of a number of facilities and equipment of the ship. However, it is noted that the ship will be delivered in time.


TFR "Admiral Grigorovich" in outfitting wall Shipyard "Yantar", 18.06.2014 (photo by Sergey Mikhailov, "Forward!" № 11/2014 г.).

- 2014 June 19 - the press service of the USC announced that the construction of a series of 6 TFR for the Russian Navy will not be completed in 2016, and in 2017 "The original contract was due date of the series - in 2016. However, since that the sixth frigate will be laid later than originally planned, then the term of delivery is really moved in 2017 "( source ). Most likely caused by a shift in timing of the termination of military-technical cooperation with Ukraine (PP production frigates).
Launching of the frigate "Admiral Essen" pr.11356R. 07/11/2014 (photo - Vitaly Nevar, http://itar-tass.com/ ).
Exports :
India
- 1997 November 17 - signed a contract for the supply of three ships total value of 1 billion. USD. - 18 June 2003 - Indian Navy frigate took the first series of INS Talwar (F40), the contract transfer was to take place in May 2002 - 2003 June 25 - Indian Navy frigate took second series INS Trishul (F43), the contract transfer was to take place in November 2002 - 19 April 2004 - Indian Navy frigate took third series INS Tabar ( F44), the contract transfer was to take place in May 2003 - 14 July 2006 - signed a second contract for the supply of three more ships pr.11356 production CVD "Amber". The contract amount - 1.6 billion. USD (533 million USD for the ship). Subtracted from the amount of the contract penalties for failure of delivery time of ships under the first contract for 1 year in the amount of 40 million. USD.
- 2007 - in the GCC "Amber" (Kaliningrad) started the construction of ships of the second series.

Frigate INS "Teg" (?), Factory №01354, after launching, Kaliningrad, 2009-2010 ( http://forums.airbase.ru ).

Frigate INS "Tarkash", factory №01355, launching ceremony, Kaliningrad, 23.06.2010 ( http://forums.airbase.ru ).
- 2010 December 16 - CVD "Amber" notified "Rosoboronexport" about the need to revise the terms of the contract with India. Requested an increase in funding for 100 million. USD and construction time. The media claimed that the value of the contract for the Indian Navy will not change.




BDK "Ivan Gren" pr.11711 (right) and pr.11356 frigate for the Indian Navy Trikand at Shipyard "Yantar", Kaliningrad, May 2011 (http://forums.airbase.ru ).
- 2011 May 25 - launched the third frigate for the Indian Navy Trikand.

INS Trikand at a ceremony launching on the CCP "Yantar" in Kaliningrad, of 25.05.2011 ( http://www.newkaliningrad.ru ).


INS Tabar (F44) pr.11356 Mod. KRIVAK-III of the Indian Navy, 2011-2012, photo (Archive Randy M, http://www.militaryphotos.net ).
- 19 August 2011 - in the newspaper "Shipwright" from the words of the chief of construction orders pr.11356 Boris Twisting reported on the state of the second series pr.11356 frigates for India:
              INS Teg (F45) - the ship is approaching the sea trials, prepares to start sea. Test the main propulsion system to be completed by 20.08.2011, the program PREPARING be completed by 25.08.2011, the
              INS Tarkash (F50) - final stage of construction, not yet put the gun mount A-190, understaffed some other vehicle systems through the fault of subcontractors. Within two months, it is planned to complete the fabrication trudoprovodov. In November 2011, the ship should start mooring trials.
              INS Trikand (F46?) - not completed grade ship lacks many types of equipment including cable of the required 150 pipe fitters on the ship is only 20. The outlook on the construction of yet.
- 2011 01 September - frigate INS Teg (F45) went on sea trials in the Baltic Sea. - 2011 November 18 - the preparation for mooring trials INS Tarkash. - 2011 December 22 - shooting from installation A-190 completed Sea trials of the frigate "Teg" for the Indian Navy. Made of fire bursts of 28 shots from the rate of fire of 70 rounds / min. Attempts to perform the scoring shooting was about ten. - 2011 December 26 - in the Baltic Sea successfully completed sea trials frigate INS Teg for the Indian Navy. Tested all systems, including missile systemBrahMos . To complete state tests left to make one out to sea in January 2012 - 17 January 2012 - Planned release date frigate INS Teg (F45) at the final stage of state tests. During sea trials frigate checked all the basic components and mechanisms, successfully conducted firing missile system BrahMos . transfer frigate of the Indian Navy is scheduled for April 2012 - 2012 07 February - CVD "Amber" state tests frigate INS Teg (F45). - 28 February 2012 - the state of work on a series of three frigates for the Indian Navy: - INS Teg (F45) - planned to convey India in April 2012. The tests are completed; - INS Tarkash (F50) - passes mooring trials; - INS Trikand (F46?) - is in the completion; - 2012 March 15 - Baltiysk started Maritime final stage of acceptance tests frigate INS Teg (F45). During sea trials necessary to replace one of the turbines of the ship. Transfer frigate India is scheduled for 27 April 2012 - 27 April 2012 - INS Teg (F45) handed over to the Indian Navy CVD "Amber".


Transfer the Indian Navy frigate INS Teg (F45) on the COR "Amber", Kaliningrad, 27.04.2012, the (photo - I.A.Mihaylov,http://forums.airbase.ru ). Transfer the Indian Navy frigate INS Teg (F45) pr.11356 second series. Shipyard "Yantar", Kaliningrad, 27.04.2012 In the background of one of the two frigates pr.11356 in- complete second series for the Indian Navy (author photo - I.A.Mihaylov, http://forums.airbase.ru ).



- 2012 May 18 - all work on the INS Tarkash (F50) completed - the ship is ready for sea trials. Start the test is scheduled for May 29, 2012 - 2012 May 24 - on the INS Tarkash (F50) officially started sea trials - the ship came to Baltiysk. Really started running out to sea June 4, 2012 Board number 703.




F45 INS Teg frigate of the Indian Navy in the port of Valletta, Malta, 27.05.2012 (photo - albireo2006,http://www.flickr.com/photos/albireo2006 ). pr.11356 Frigate INS Tarkash sea trials, summer 2012 . ( http://www.shipyard-yantar.ru ).pr.11356 Frigate INS Tarkash sea trials, Baltic, summer 2012 (file photo Vyacheslav Semenkova, http://forums.airbase.ru ).






- 2012 August 25 - in the media reported that sea trials INS Tarkash (F46) in the Baltic Sea successfully completed. In September, the ship returned to Kaliningrad and the official transfer of the ship is scheduled for India in November 2012 - 2012 September 15 - on the ship INS Trikand announced the beginning of the mooring trials.


INS Trikand on CVD "Amber", Kaliningrad, of 15.09.2012 ("Forward!", №17, 28.09.2012 city). INS Tarkash F50 on CVD "Amber", Kaliningrad, 27.10.2012 Mr. . (photo - 39rus, http://forums.airbase.ru ).



- 2012 09 November - in Kaliningrad on CVD "Yantrar" to be held the ceremony of transfer of the second ship of the Indian Navy frigates pr.11356 second series - INS Tarkash (F50). Transfer the third ship INS Trikand expected summer 2013 after sea trials, which will begin in the spring of 2013


Frigate INS Tarkash F50 at the handover ceremony of the Indian Navy, the GCC "Amber", Kaliningrad, November 9, 2012 (photo - I.A.Mihaylov,  http://forums.airbase.ru , assembly). Frigate INS Tarkash F50 at the handover ceremony of the Indian Navy, the GCC "Amber", Kaliningrad, November 9, 2012 (photo - I.A.Mihaylov, http://forums.airbase.ru ).



- 2012 November 12 - in the Russian media quoted one of the officials has information about the plans of the Indian contract for the construction of three more frigates pr.11356. In the case of confirmation of this information in the case of performing such a contract in the Indian Navy will be 9 frigates pr.11356. At the beginning of February 2013, this information is not confirmed by our Indian sources of information. - 2012 December 27 - the frigate INS Tarkash F50 arrived in India ( source ). - 2013 February 14 - frigate INS Trikand pr.11356 released in Baltic sea trials. The official start of the test - February 8 - the day before the ship moved from akvatarii SRH military harbor Baltiysk ( source ). - 2013 04 March - began training Indian crew INS Trikand. On April 1, 2013 will ship crew practice, and on May 2 is scheduled to begin acceptance testing of the ship. the transfer of the ship of the Indian Navy is scheduled for June 2013 ( source ). - 2013 March 14 - frigate INS Trikand pr.11356 factory completed sea trials. During the tests performed five ship goes to sea, includingperformed firing artillery unit ( source ).  - 2013 April 17 - frigate INS Trikand pr.11356 completed state tests of the sea. The tests were started April 4, 2013 in Baltiysk. Since April 8 regularly ship out to sea polygons of the Baltic Fleet, which showed the state commission all systems and mechanisms, including weapons. March 17 plant commissioning team and the crew of the Baltic Fleet conducted missile firing anti-aircraft complex "Calm-1." "As a result of firing was struck by a missile target moving at a height of 50 m above sea level - the project manager 11356 Shipyard" Yantar "Alevtin Dmitriev ( source ). - 2 May 2013 - is scheduled to begin acceptance testing frigate INS Trikand pr.11356 ( source ). - 2013 May 22 - off the coast of Goa made ​​successful launch of BrahMos, the missile range - 290 km. The missile carried a C-shaped maneuver in height. Start was first produced from the frigate INS Tarkash pr.11356 Indian Navy.


Start missile BrahMos on board the frigate INS Tarkash pr.11356, 22.5.2013, the ( http://www.npomash.ru ).

- 2014 August 13 - the media reported that the upcoming India tenders for new frigates will be offered three ships pr.11356 Russian propulsion ( source ). Register frigates so on. 11356:



projectserial numberplantlaidlaunchedcame into operationnote
INS Talwar (F40)pr.11356301CVD "Baltic Plant"10.03.199912.05.200019.03.2002 (Russia)
18.06.2003
(India)
"Sentinel" in the Russian Navy
INS Trishul (F43)pr.11356302CVD "Baltic Plant"24.09.199924.11.20002002 (Russia)
25.06.2003 (India)
"Impact" in the Russian Navy
INS Tabar (F44)pr.11356303CVD "Baltic Plant"26.05.200025.05.20012004 (Russia)
19.04.2004 (India)
SKR-23 in the Russian Navy
INS Teg (F45)pr.1135601354CVD "Amber"28-07-200727.11.2009Plan mid-2011 (2010) plans to start in 2012 (Fall 2011) plan in April 2012 (16.01.2012 g)Plan of 27.04.2012 (28.03.2012 g)27.04.2012 g .







for the Indian Navy, port - Visakhapatnam
INS Tarkash (F46)pr.1135601355CVD "Amber" responsible deliverer - Sergei Shchugorev27.11.200723.06.2010Plan 2011-2012, (2010)Plan 2012 (Autumn 2011, April 2012)Plan - October 2012 (04.07.2012 g)Plan - November 2012 (24.08.2012 g)09.11.2012 g .







for the Indian Navy, aboard №703 during trials in the Baltic Sea
INS Trikand (F50)pr.1135601356CVD "Amber"12.06.2008planned in 2010 , the 25.05.2011
Plan 2012 (2010) Plan - June 2013 (autumn 2011, confirmed - March 2013)Plan - 29.06.2013g.(11/06/2013 city, confirmed 25.06.2013)06.29.2013, the





for the Indian Navy 
"Admiral Grigorovich"pr.11356R01357CVD "Amber", a senior builder - Alexander Sitnov, by July 2013 - Igor Protas ( source)Plan in November 2010 (summer 2010) 18.12.2010

Plan - 2012 (December 2011)Plan - 2013 (14.09.2012 g)Plan - Fall 2013 (March 2013) Plan - February 2014 (30.01.2014g.)Plan - March 2014 (02/24/2014 city) , the 14/03/2014









Plan 2013 (2010), Plan 2014 (2011, March 2013, spring 2014)Spring 2015 (plan for November 2014)


№1 for the Black Sea Fleet of the Russian Navy - 02/24/2014 city - launching the ship moved for a month due to the difficult ice conditions
"Admiral Essen"pr.11356R01358CVD "Amber"08.07.2011 (18.12.2010 plan and the actual date bookmark)Plan - September-October 2014 (28.08.2014 g) of 11.07.2014
Plan 2014 (2011) forecast - 2015 (2014)
№2 for the Black Sea Fleet of the Russian Navy (previously stated, it is possible to remain at BF).Probably, construction halted in 2014 due to lack of propulsion.
"Admiral Makarov" (in terms of sources in 2010-2011 mentioned the name "Admiral Kolchak")

pr.11356R01359CVD "Amber", a senior builder - Alexander KrupnyakovPlan December 2011 (first half 2011) Plan in February 2012 (December 2011) of 29.02.2012


-Plan 2014-2015 gg (2011) Plan 2015 (2012)
№3 for the Black Sea Fleet of the Russian Navy.Probably, construction halted in 2014 due to lack of propulsion.
"Admiral Butakov" (in terms of sources in 2010-2011 mentioned the name of "AdmiralKornilov ")

pr.11356R01360 (source,source)CVD "Amber"Plan Fall 2012 (2011) plan - 12.10.2012 g (12.10.2012, the media) plan - 03.20.2013 g (05.03.2013 g) plan - 04.18.2013, the (4/15/2013 city, moved to the later date of 16.04.2013)07.12.2013, the







-Plan 2015-2016 gg (2011)№4 for the Black Sea Fleet of the Russian Navy.The contract for construction was signed in 2011. Perhaps the construction halted in 2014 due to lack of propulsion.
"Admiral Istomin" (2011, confirmed by the message Commander of the Black Sea Fleet Navy A.Fedotenkova, 04/29/2013 city)pr.11356R01361CVD "Amber"Plan 2013 (2011)plan - 11.15.2013, the (11/08/2013 city) , the 15/11/2013


-Plan 2015-2016 gg (2011)№5 for the Black Sea Fleet of the Russian Navy.The contract for construction was signed in 2011. Perhaps the construction halted in 2014 due to lack of propulsion.
"Admiral Kornilov" 
(2011, confirmed by the message Commander of the Black Sea Fleet Navy A.Fedotenkova, 04/29/2013 city)
pr.11356R01362CVD "Amber"Plan 2013 (2011)Plan - 2014 (24.02.2014 g)
-Plan 2015-2016 gg (2011) Plan - 2017 (06.19.2014 g)

№6 for the Black Sea Fleet of the Russian Navy.The contract for construction was signed in 2011. Perhaps the construction halted in 2014 due to lack of propulsion.
??pr.11356M
?

Amur CVD g.Kosmomolsk-on-Amur--Plan to 2020 (2011)№7 for the Russian Navy.according to the state program of development of weapons for 2011-2020, GG, PF
??pr.11356M
?

Amur CVD g.Kosmomolsk-on-Amur--Plan to 2020 (2011)№8 for the Russian Navy. in accordance with the state program of development of weapons in 2011-2020 GG, PF
??pr.11356M? ?--Plan to 2020 (?)№9 for the Russian Navy (source , 30/01/2014 city).
Italics are marked tentative data. Board number:


 "Admiral Grigorovich""Admiral Essen""Admiral Makarov""Admiral Butakov""Admiral Istomin""Admiral Kornilov"
2014      
2015      

Frigates project in the fleet:
YearTotal Navy"Admiral Grigorovich""Admiral Essen""Admiral Makarov""Admiral Butakov""Admiral Istomin""Admiral Kornilov"
20140- 05.15.2014, the - the ship set artillery unit A-190
- November - the ship passes doshvartovny period.
- end of November - the beginning of the planned mooring trials.
- 11.07.2014, the - ship launched already installed artillery unit A-190 
---
20151- Spring - is expected to pass the Navy ship

   



Sources :
Russian Navy. Site http://ru.wikipedia.org , 2012
Jekel V., A. Adams on "Amber" began to build another frigate. Site http://kaliningrad.rfn.ru , 2011 transferred to the Indian Navy frigate Trishul, built at the Baltic Shipyard . Interfax-AVN, June 25, 2003
Kartushina T. The crew of the frigate combat. // Shipwright. 19.08.2011 was
to Lenta.ru. 2010-2012 gg
Russia will complete tests of the first frigate for India. Site http://flotprom.ru , 16.01.2012, the
site "Vestnik PVO" ( http://pvo.guns.ru ), 2008 ..
CVD "Amber" completes a year of planning work to order. Site http://flotprom.ru , 20.12.2011, the
fear has passed. Site http://blog.fontanka.ru , 24.02.2011, the
Balancer.Ru forums. Site http://forums.airbase.ru , 2011
Russian-Ships.info. Site http://russian-ships.info , 2010
Wikipedia. The Free Encyclopedia. Site http://en.wikipedia.org , 2010